Welcome to our new homes page. This page will show the progress step by step as we build our new homes. It will also have commentary by the builders and Realtors as we go along as to what has been happening. In the end the new owner will get to see how their new quality home came to be a home. 
SO INTRODUCING 
2013 FALLING LEAVES LEXINGTON, KY 40509

SITE SELECTION: JULY 2014


CLOSE ON LOTS: AUG 22 2014

DESIGN: AUGUST 28 2014

FIRST SET OF PLANS: SEPT 3 2014

PLAN CHANGES COMPLETE: SEPT 9 2014
JLH Plan


GROUND WORK: SEPT 29, 2014


RAIN DELAY: OCT 2 - OCT OCT 15TH


PERMIT: 10/21/14

FOOTERS DUG: (FINALLY) OCT 28 2014
Thanks to the engineers at L.E. Gregg for coming quickly to inspect the footers (again to be sure) due to the area being filled in areas in the past. They do a great job and are great to work with.


FOOTERS POURED: OCT 29 2014



RAIN DELAYS...AGAIN






11/4/14






11/5/14 and 11/6/14

Guess what....


Nov 7th
Footers pinned and marked
(So they know where to place basement walls)




11/10/14
Walls forms are going up, more dirt moved too


11/12/14
Almost ready to pour basement walls. This is going to be a big basement.







11/13/14

Walls Poured


11/16/14

It got cold and snowy so did not get much done this weekend.
11/17/14


Got more dirt...that's about it.


11/20/14
Basement Waterproofed and fill dirt coming in


The next two weeks in a nutshell
11/21 - 12/5/14

Rain and Rocks



Dec 5- 9th

Rain, Rocks, and Dirt








December 10 

Rough in Plumbing is in, more dirt, yard starting to look like a yard, almost. 




Dec 11-16

Leveling and ready to pour basement floor


Dec 17th Poured Floor and leveled lot with MORE dirt, ready to start framing






Dec 17-20
Waiting on Framers


Dec 22nd
They started Framing

Dec 23rd
First Floor about done the guess what...Rain

Dec 24
Now we are really Rolling








Dec 26th


Dec 27th

Dec 30th
Trusses up, mostly.

Jan 1-Jan 3
Framing Away


Jan 3



Jan 7



Jan 8

Jan 8 -12
Plumbing continues






Jan 12-16
Windows,  Doors, Plumbing testing, Duct Work









Jan 20-Feb 1
A lot happened here....
 Rough in inspections completed


 Front Bricks Done

Brick Skirt almost done

We are now officially Listed for Sale:

2013 Falling Leaves LBAR Listing