Welcome to our new homes page. This page will show the progress step by step as we build our new homes. It will also have commentary by the builders and Realtors as we go along as to what has been happening. In the end the new owner will get to see how their new quality home came to be a home.
SO INTRODUCING
2013 FALLING LEAVES LEXINGTON, KY 40509
SITE SELECTION: JULY 2014
CLOSE ON LOTS: AUG 22 2014
DESIGN: AUGUST 28 2014
FIRST SET OF PLANS: SEPT 3 2014
GROUND WORK: SEPT 29, 2014
RAIN DELAY: OCT 2 - OCT OCT 15TH
PERMIT: 10/21/14
FOOTERS DUG: (FINALLY) OCT 28 2014
Thanks to the engineers at L.E. Gregg for coming quickly to inspect the footers (again to be sure) due to the area being filled in areas in the past. They do a great job and are great to work with.
FOOTERS POURED: OCT 29 2014
RAIN DELAYS...AGAIN
11/4/14
11/5/14 and 11/6/14
Guess what....
Nov 7th
Footers pinned and marked
(So they know where to place basement walls)
11/10/14
Walls forms are going up, more dirt moved too
11/12/14
Almost ready to pour basement walls. This is going to be a big basement.
11/4/14
11/5/14 and 11/6/14
Guess what....
Nov 7th
Footers pinned and marked
(So they know where to place basement walls)
11/10/14
Walls forms are going up, more dirt moved too
11/12/14
Almost ready to pour basement walls. This is going to be a big basement.
11/13/14
Walls Poured
11/16/14
It got cold and snowy so did not get much done this weekend.
11/17/14
Got more dirt...that's about it.
11/20/14
Basement Waterproofed and fill dirt coming in
The next two weeks in a nutshell
11/21 - 12/5/14
Rain and Rocks
Dec 11-16
Leveling and ready to pour basement floor
Dec 17th Poured Floor and leveled lot with MORE dirt, ready to start framing
Dec 17-20
Waiting on Framers
Dec 22nd
They started Framing
Dec 23rd
First Floor about done the guess what...Rain
Dec 24
Now we are really Rolling
Dec 26th
Dec 27th
Dec 30th
Trusses up, mostly.
Jan 1-Jan 3
Framing Away
Jan 3
Jan 7
Jan 8
Jan 8 -12
Plumbing continues
Jan 12-16
Windows, Doors, Plumbing testing, Duct Work
Jan 20-Feb 1
A lot happened here....
Rough in inspections completed
Front Bricks Done
Brick Skirt almost done
We are now officially Listed for Sale:
2013 Falling Leaves LBAR Listing
11/20/14
Basement Waterproofed and fill dirt coming in
The next two weeks in a nutshell
11/21 - 12/5/14
Rain and Rocks
Dec 5- 9th
Rain, Rocks, and Dirt
December 10
Rough in Plumbing is in, more dirt, yard starting to look like a yard, almost.
Leveling and ready to pour basement floor
Dec 17th Poured Floor and leveled lot with MORE dirt, ready to start framing
Dec 17-20
Waiting on Framers
Dec 22nd
They started Framing
Dec 23rd
First Floor about done the guess what...Rain
Dec 24
Now we are really Rolling
Dec 26th
Dec 27th
Dec 30th
Trusses up, mostly.
Jan 1-Jan 3
Framing Away
Jan 3
Jan 7
Jan 8
Jan 8 -12
Plumbing continues
Jan 12-16
Windows, Doors, Plumbing testing, Duct Work
Jan 20-Feb 1
A lot happened here....
Rough in inspections completed
Front Bricks Done
Brick Skirt almost done
We are now officially Listed for Sale:
2013 Falling Leaves LBAR Listing